MAHB imposes LAD penalty of RM9.1m on KLIA aerotrain contractors – 91 days late, RM100k a day

MAHB imposes LAD penalty of RM9.1m on KLIA aerotrain contractors – 91 days late, RM100k a day

If your new property isn’t handed over by an agreed date as stated in the sale and purchase agreement, the developer has to pay liquidated ascertained damages (LAD) to buyers. LAD also exists in government infrastructure projects, and the compensation is RM100,000 per delayed day for the KLIA aerotrain.

As the KLIA aerotrain contractors were 91 days late in handing over the the project, Malaysia Airports (MAHB) is claiming a LAD penalty of RM9.1 million from Alstom IJM Construction and Pestech Technology, which are the two parties in the IJMC-Pestech joint venture. The 91 days are from April 1, 2025 till June 30, 2025, reported by Bernama.

The new KLIA aerotrain had a less-than-smooth start to life, but earlier this month, MAHB said an independent rail assessor confirmed that the system was operating as planned, with service disruptions being typical in the early operational phase of a complex rail system.

The assessor reportedly found that the disruptions did not pose a safety risk as structured engineering controls and ongoing monitoring were in place to effectively manage the issues – full story here.

Looking to sell your car? Sell it with Carro.

Certified Pre-Owned - 1 Year Warranty

Renew your car insurance with us

Compare prices between different insurer providers to save the most on your car insurance renewal compared to other competing services. Many payment method supported and you can pay with instalment using Atome, Grab PayLater or Shopee SPayLater.

Renew Car Insurance

Danny Tan

Danny Tan loves driving as much as he loves a certain herbal meat soup, and sweet engine music as much as drum beats. He has been in the auto industry since 2006, previously filling the pages of two motoring magazines before joining this website. Enjoys detailing the experience more than the technical details.

 

Comments

  • Johnny on Feb 27, 2026 at 12:06 pm

    You can impose but whether you get paid, that’s another story. Hope MAHB can publicly announce after they successfully get the 9.1m from contractors.

    Thumb up 1 Thumb down 0
  • Kea Was on Feb 27, 2026 at 1:18 pm

    So is the LAD being paid by the actual contractor or tax payers money one wonder?

    Thumb up 1 Thumb down 0
  • haers gnna hae on Feb 27, 2026 at 1:25 pm

    the only solution to this is to let a type C company run klia aerotrain , for example look at how problem-free KLia Ekspres is because its operated by YTL

    Thumb up 1 Thumb down 0
  • can sit down drink a coffee and bincang. 90k plus one new landed unit for mahb boss by ijm. settled.

    Thumb up 0 Thumb down 1
 